Weathered cedar-shingle hillside home opening onto a sandstone terrace, with a teak bench, oak canopy and stone-bordered planting.

Sausalito's Downtown Waterfront Is Being Rebuilt One Grant at a Time

A 1/12th-scale model of the Excelsior Stairs is on display at the City Hall library branch. It shows the 52 gray concrete steps above Bridgeway at Bay Street with a painted mural running up the risers. Supporters brought it to the City Council meeting on Oct. 5, and the model now stands in for a mural that has a $100,000 budget and, as of mid-October, a little over $15,000 raised.

That model shows how the downtown waterfront is being rebuilt right now. The ferry plaza, the stairs, the Turney Street boat ramp and Parking Lot 1 each have a separate funding stream, and none of them depends on one large city budget line. Federal transit dollars, a state boating grant, a county arts grant, donations from businesses and volunteer planting crews are each paying for a different piece. Each project moves only as fast as its own funding, which explains why the finished promenade at Tracy Way sits next to a parking lot that is still being designed.

The promenade that outside money built

The Ferry Landside Improvement Project is the one that's done. The process began in 2017, construction started in September 2024, and the City called it a $2.5 million grant-funded project paid for by the Federal Transit Administration, the Golden Gate Bridge, Highway and Transportation District and the City of Sausalito. The City's January 2025 project summary breaks that out as $2 million from the FTA, $400,000 from the Bridge District and a $100,000 local match. So roughly four of every five dollars came from federal transit money.

The work made the ferry entry plaza larger and turned Tracy Way into a pedestrian promenade between Parking Lot 1 and Viña del Mar Park. It also added new trees, pedestrian and bike paths, separate ferry queuing areas, accessible parking, bike parking and sidewalks around Lot 1 and Gabrielson Park. The City's project page records a $1,416,000 construction award to Bauman Landscaping.

The City's newsletter credits Vestre with the dark- and light-blue benches and tables on Tracy Way Plaza and Tournesol Siteworks with the planter pots. Public Works staff assembled the furniture. Public Works maintenance crews, Sausalito Beautiful volunteers and the local SWA office planted the planters. The Marin Independent Journal reported that downtown businesses contributed the blue-themed benches, the picnic tables and the hanging flower baskets. In the same article, Adrian Brinton, founder of Positive People for Sausalito, said the redesign made the landing "more of a usable public space."

The space now has a regular schedule. Sausalito Art & Harbor Days takes over Tracy Way, Ferry Landing Plaza and Gabrielson Park on the fourth Saturday of every month in 2026 with local makers and live music, and the next two dates are Nov. 28 and Dec. 26, 10 a.m. to 5 p.m. The Downtown Sausalito Association's 5th Annual Holiday by the Bay Tree Lighting is also at Tracy Way Plaza, on Thursday, Dec. 3. Festivities start at 5:30 p.m., and the tree is lit at 6:15.

Fifty-two risers, paid for step by step

The Excelsior Stairs mural is a few hundred feet from Tracy Way, across Bridgeway from Viña del Mar Park, and it depends even more on donations than the plaza did. The Marin IJ reported that the council voted Oct. 5 to accept the donated mural. It would be the town's first new public art in more than 30 years.

Sausalito artist Raylene Gorum, who designed the "All Our Children United" mural on the Highway 101 underpass between Sausalito and Marin City, will paint it. The nonprofit Sausalito Sister Cities is the sponsor. The design shows two women embracing a globe of the western hemisphere. At the bottom is Gabriela Mistral, the Nobel Prize-winning Chilean writer, above a dress whose pleats are rows of grapevines. At the top, under a flower-filled arbor, is a Sausalito woman. Viña del Mar became Sausalito's first sister city in 1960, and the stairs face the park that carries its name.

The mural is the first approval under the five-step public-art review the council adopted earlier this year. Mayor Steven Woodside told the IJ, "This is going to spark more projects in town and this is a spectacular start to that."

The plan for raising the money is literal. As of the IJ's report, the project had a $5,200 county grant and a $10,000 donation toward its $100,000 budget. Robert Miros, a Sausalito Sister Cities board member, described the approach to the paper this way:

"Our plan is to 'sell steps,' meaning that at certain levels of funding you will be recognized as having supported a specific step. Details are still coming together."

The group hopes to paint the stairs by next spring. Before any paint goes on, the project is asking the City to power wash and prep the stairs, which could cost $8,500. The schedule depends on how quickly the 52 steps are sponsored.

Turney Street shows how slow grant money can be

North along Bridgeway, the Turney Street boat ramp shows what happens when the funding comes together slowly. The ramp and its docks are a rare public access point to Richardson Bay, and the City has talked about renovating them for years. According to the Marin IJ's September report, this is the order of events:

  1. Late 2024. A $170,000 state Fish and Wildlife boating-access grant arrives, plus $104,000 from the City's Tidelands Fund, to pay for preliminary engineering, environmental review and design options.
  2. Last winter. The council seeks a public-private partnership in which a business would help pay for construction in exchange for favorable lease terms. A preferred partner was chosen in the spring, but staff said the effort stalled.
  3. Sept. 15, 2026. The council unanimously selects a design.
  4. 2026. Engineering.
  5. 2027. Lining up funding and state and federal permits.
  6. 2028. Construction, with an early estimate of $3.1 million.

The design replaces and extends the ramp into Richardson Bay and replaces the weathered bulkhead. It adds docks for up to 16 small, shallow boats in front of the Joinery and a second gangway behind Salito's leading to docks for a dozen dinghies, along with access for kayaks, paddleboards and swimmers. Deep-keel sailboats won't be able to use it, because that part of the bay is shallow and dredging would require federal permits. Vice Mayor Melissa Blaustein told the IJ she has "a personal interest in being able to swim up to the boat launch safely."

Side by side

All four waterfront projects in one place:

Project Where it stands for fall 2026 Money on record Where it comes from
Tracy Way and Ferry Landing Complete; ribbon-cutting Sept. 5, 2025 $2.5 million in grants and match, $2.62 million with Tidelands revenue in the January 2025 summary Federal transit funds, the Bridge District, a City match, plus donated furniture and volunteer planting
Excelsior Stairs mural Approved Oct. 5, 2026; target spring 2027 $100,000 budget, about $15,200 raised County grant, private donations, "sell steps"
Turney Street ramp and docks Design selected Sept. 15, 2026; construction 2028 $3.1 million early estimate State grant and Tidelands funds so far; construction funding to be lined up in 2027
Parking Lot 1 In design $2.5 million overall project budget Parking Fund and Tidelands revenue, though $1.205 million of the Parking Fund share was not in the 2025/26 capital plan

The ferry landing, built mostly with federal transit money, is finished. Turney Street, where a private partner was supposed to help cover construction, still has to line up that funding.

Parking Lot 1 is the gap in the middle

The Tracy Way promenade starts at Parking Lot 1, and Lot 1 is the next piece. The ferry project didn't resurface the lot, according to a June 16, 2026 City staff report. That report describes continuing design coordination for Lot 1 and the streets around it, increases the CSWST2 design contract by $45,000 to $288,393, and shows a $2.5 million overall project budget. The City's project page says the goal is to keep the current number of parking spaces while rethinking trees, circulation for pedestrians, bikes and cars, paving materials and green infrastructure.

In February, the Marin IJ reported a target finish of spring 2027. The June staff report says the expanded design work will take many months, so that date is best treated as open. For now, the lot is the unfinished piece next to the finished plaza.

Downtown events through the boat parade

These downtown events use the new and older public spaces between now and mid-December:

  • SCA Open 2026, the free juried exhibition at the Sausalito Center for the Arts, 750 Bridgeway, runs through Dec. 6. Gallery hours are 11 a.m. to 5 p.m. on the listed November dates. Details.
  • Sausalito Players: The Long Christmas Dinner, Wednesday, Nov. 11, 7 to 9:30 p.m., and ICB Art Open Studios, Friday, Nov. 13, 5 to 8 p.m., both on the Downtown Sausalito calendar.
  • Art & Harbor Days, Saturday, Nov. 28, 10 a.m. to 5 p.m., on Tracy Way, Ferry Landing Plaza and Gabrielson Park. The Sausalito Farmers Market runs every Sunday, 9 a.m. to 2 p.m., in the Dunphy Park parking lot at 1600 Bridgeway. City listing.
  • Holiday by the Bay Tree Lighting, Thursday, Dec. 3, at Tracy Way Plaza, with the tree lit at 6:15 p.m.
  • Winterfest Lighted Boat Parade, Saturday, Dec. 12, 6 to 7:15 p.m., along the waterfront at Gabrielson Park, with fireworks at about 7:15. Winterfest Sausalito.

The mural's scale model is still at the City Hall library branch, and the stairs it shows are a short walk from the Tracy Way benches the businesses donated.

If you're curious how Sausalito's public waterfront projects affect the streets around them, or you'd like a local's walk down Bridgeway this season, I'm always glad to talk it through. Alexandra Cowley. Let's Connect.

Work With Alexandra

Buying or selling a home is one of life's biggest decisions, and having the right advisor makes all the difference. With strategic guidance, skilled negotiation, and a client-first approach, every step is thoughtfully managed to help you achieve the best possible outcome. The goal is to make your next move seamless, successful, and aligned with your long-term goals.